The Grohnde nuclear power plant in Lower Saxony stopped producing in 2021. On the same ground, today, they are growing three giant battery storage systems: 1,47 gigawatts of combined power, over 6 gigawatt hours of capacity, on 35 hectares of industrial land. The total exceeds the net power of the reactor they shut down (1,36 GW). Three operators are working on the project: GESI, FRV, Elements Green. All will connect to the new Emmerthal substation which TenneT It's being built to replace the one in Grohnde, which is now underpowered. The interesting detail isn't so much the symbolic nuclear-battery symmetry. It's something else.
The batteries are due to arrive in 2026. The substation that will have to distribute their current towards the large high-voltage lines, however, will be ready by the end of 2030. And the two mega direct current lines that economically justify the investment, RheinMainLink e SüdLink, will arrive respectively in 2033 and (perhaps) in 2028.
They are building energy storage for a grid that doesn't yet exist, looking to an electric future.
The Emmerthal energy cluster in numbers
The plan of the municipality of Emmerthal includes up to three BESS (battery energy storage systems) on the 35 hectares of the energy cluster. GESI, of which Allianz Global Investors recently acquired a 51% stake, will install containers with cells lithium iron phosphate for 870 megawatts of power and 3,84 GWh of capacity. It's a 4-hour system: means that, discharged at full power, it lasts exactly four hours before running out. FRV, a Spanish partner, will build a second 600 MW, 2,4 GWh BESS alongside it, combined with a 53-hectare ground-mounted photovoltaic park operated by Solizer (72 MWp peak). This one, too, will be 4 hours.
The British Elements Green It hasn't yet released the numbers for Emmerthal, but it's about to invest €2 billion in Germany and is building a 400 MW facility in Elsfleth. If it replicates the same size here, the cluster will reach 1,87 GW and 7,8 GWh overall. To give you an idea: across Germany, currently, according to battery-charts.de, large-scale energy storage systems in operation account for 5,2 GWh for approximately 3,2 GW. Emmerthal alone would require more than 50% of the current national total. I emphasize, alone.
Where the accumulation arrives, and where it does not pass through
The site's declared strength is its location: the Emmerthal substation will connect two 380 kV lines (both slated for upgrade) with several 110 kV lines. Nearby, less than 19 kilometers away, is the future RheinMainLink HVDC line, the sister project to the SüdLink line currently under construction: 525 kV direct current underground cables, designed to carry surplus wind power from the windy north to the electricity-hungry south.
The calculation made by the operators is quite transparent: buy the excess wind energy in the North at a low price, resell it at a high price in the South when needed. Except that The H, who followed the dossier, had to correct an important detail in the original piece: an HVDC converter station is not planned in Emmerthal. The DC lines, at least for now, have converters only at the ends. Translation: the energy from the batteries will travel on the AC grid, not directly connected to the DC highways. The business plan figure remains the same, but the equipment does not.
Accumulation comes before the grid
I'm returning to the point of the article. Operators are talking about BESSs entering service "starting in 2026." The Emmerthal substation, however, will only be completed at the end of 2030: 25 hectares of new infrastructure to manage the flow. SüdLink hopes to complete construction in 2028 (they hope, indeed). The RheinMainLink, which is expected to transport 8 GW from north to south, is scheduled for completion in 2033. In short, when the first batteries begin to charge and discharge, the complete network for which they were designed will be at least four years away.
Meanwhile, the existing 380 kV lines will be upgraded with an interesting trick: TenneT provides for the re-stringing, that is, the replacement of overhead cables with aluminum-steel conductors capable of withstanding temperatures of up to 150°C, a coating to improve thermal radiation, and a current carrying capacity up to 50% higher than the old cable of the same diameter. It's a temporary workaround to allow more electricity to pass through the existing pylons while waiting for the new ones to arrive. An elegant, stopgap solution.
project sheet
Sito: Energiecluster Emmerthal, municipality of Emmerthal (Lower Saxony), next to the former Grohnde nuclear power plant, which shut down in 2021.
Operators and sizesGESI (870 MW / 3,84 GWh, 4-hour system, LiFePo batteries), FRV “Grohnde III” (600 MW / 2,4 GWh, combined with a 72 MWp Solizer photovoltaic system), Elements Green (size not yet declared, presumably 400 MW). Total potential: 1,47-1,87 GW, capacity 6,24-7,8 GWh.
Comparison: The Grohnde nuclear power plant had 1,36 GW net. Pig iron: heise online (c't Magazin), "1.4 GW: Huge battery storage at former Grohnde nuclear power plant” by Christof Windeck, updated April 29, 2026.
The German model and its effect on Italy
Germany is today the leading European market forbacklog industrial-scale battery power, driven by the demand for flexibility that the decarbonization of the electricity mix produces. Italy follows in third place, ahead of much of the continent: the driver is the MACSE, the strategic storage capacity award mechanism managed by Terna, which, with contracts lasting up to 15 years, made the first auction competitive. At the end of June 2025, storage systems in Italy reached a total of nearly 16,5 GWh, largely driven by large utility-scale projects. The industrial model seen in Grohnde is not a German exception; it is the European model for the next five years.
The Italian detail is that we don't have the reactors to shut down, but we have the mirror problem: renewables that are rising rapidly and a network that is struggling to digest themEven in our country, every large BESS faces authorization delays, network congestion, and the usual bureaucratic process that sends containers out before the transmission lines that are supposed to house them. Well, that's the pattern. That's fine, because that's the trajectory, but it must be said.
Meanwhile, the game is being played upstream regarding materials: who recovers lithium from used batteries, and who gives them a second life. 90% declared by the Japanese plant in Fukui It's a good number, but the problem is the logistics of recycling. And regarding domestic storage, the discussion is still different: the modular residential (the systems 5 kWh “drawer” type (which you see in retailers' warehouses) travels on a completely different scale, but it also enters into the accounts of the network authorities.
When will we really see it?
Estimated horizon: 4 7-years for the full operation of the Emmerthal cluster. The first batteries will be installed by 2026, but the system will only be fully operational once the Emmerthal substation is commissioned (late 2030) and SüdLink is completed (planned for 2028). RheinMainLink by 2033 is the real bottleneck for the North-South arbitrage business model.
The first to benefit will be grid balancing operators and financial investors (Allianz GI has already acquired a 51% stake in GESI, and Obton has purchased the nearby Kyon Energy BESS). German household bills will react later, and indirectly. The detail that puts things into perspective: four years of misalignment Between ready batteries and a ready network, this means four years of expensive assets that will work below their technical capacity, on a network that tolerates them but does not value them.
Meanwhile, the Grohnde cooling tower is still there, awaiting dismantling. Seen from a certain angle, it appears to be standing guard over the containers replacing it. It's perhaps the most literal energy transition Germany could stage: the same grid, the same terrain, two different technologies taking turns.
With the small detail that the new one arrives before the infrastructure that should house it. (In Italy it would almost seem familiar to us, wouldn't it?)